answertrivia posted: " Answer: (crash cost - normal cost)/(normal time - crash time) Which of the following correctly calculates an activity's cost slope?A.(normal cost - crash cost)/(normal time - crash time)B.(crash cost - normal cost)/(normal time - crash time)C."
|
ANSWERTRIVIA.COM: We ask you, humbly: don't scroll away.
Dear Reader, If you use ANSWERTRIVIA a lot, this message is for you. We're sure you are busy so we'll make this quick: Today we need your help. We don't have salespeople. We depend on donations from exceptional readers, but fewer than 2% give. If you donate just a coffee, lunch or whatever you can today, ANSWERTRIVIA could keep thriving. Thank you.
We Answer Your Questions, Search Now!
Friday, 19 March 2021
[New post] [Answer] Which of the following correctly calculates an activity’s cost slope?A.(normal cost – crash cost)/(normal time – crash time)B.(crash cost – normal cost)/(normal time – crash time)C.(normal time – crash time)/(crash cost – normal cost)D.(normal time – crash time)/(normal cost – crash cost)E.(crash cost – normal cost)/(crash time – normal time)
Subscribe to:
Post Comments (Atom)

No comments:
Post a Comment